Handover Watch, October 2026: Dubai Projects Due for Completion in the Next 9 Months

By Mohammed Umar Zakaria · 11 October 2026 · 3 min read

The short answer: 48 registered Dubai projects have completion dates between September 2026 and July 2027 in the Dubai Land Department’s latest open data. Some are nearly finished; others are far behind their registered date, which usually means the date will move. If you own a unit in one of them, now is the time to plan your final payment, snagging, and whether to sell, lease or move in.

How to read this

Figures come from the DLD’s Real Estate Projects register (snapshot dated 15 June 2026): each project’s registered completion date and the construction percentage recorded at that time. Construction has continued since then, and registered dates can be revised, so treat this as an early warning, not a final schedule. Tap any project to see its page and follow it: you’ll get an email when the DLD data changes.

Close to completion (60% or more built)

ProjectDeveloperRegistered completionBuilt (June 2026)
The Valley – EloraEmaarSep 202689%
Azizi Riviera 55AziziMar 202785.6%
Arabian Ranches III – Anya 2EmaarDec 202676.8%
Golf HeightsEmaarDec 202670.2%
Arabian Ranches III – AnyaEmaarOct 202668.4%
Azizi Riviera 56AziziMar 202767.7%
The Valley – RivanaEmaarMar 202764.2%
Palm Beach Towers 2NakheelDec 202664.1%
Palm Beach Towers 1NakheelDec 202663.6%
City Center ResidencesEmaarSep 202663.6%

Watch list: big gap between date and progress

These projects had registered completion dates in 2026 but were less than 30% built in June. A gap this size usually means the completion date will be revised, so check the latest schedule with the developer before you plan around it.

ProjectDeveloperRegistered completionBuilt (June 2026)
Binghatti AquariseBinghattiOct 2026Not started
Central Park Plaza, City WalkMeraasOct 202610.7%
Bay Residences, Dubai IslandsNakheelOct 202619.1%
Lanai Island, Tilal Al GhafMajid Al FuttaimSep 202619.4%
Mercedes-Benz PlacesBinghattiDec 202626.1%

In progress (30–60% built)

ProjectDeveloperRegistered completionBuilt (June 2026)
Palm Beach Towers 3NakheelDec 202656.9%
Marina ShoresEmaarDec 202654.2%
Oasis Residences 02, Expo CityExpo City DubaiJun 202748.2%
Oasis Residences 01, Expo CityExpo City DubaiJun 202746.7%
Sobha Hartland Waves OpulenceSobhaSep 202646.6%
Fairway Villas 2, Emaar SouthEmaarDec 202645.8%
Mudon Al Ranim 7Dubai PropertiesSep 202643.8%
Mudon Al Ranim 8Dubai PropertiesSep 202643.2%
Beach Gate by AddressEmaarDec 202642.9%
The St. Regis Residences, DowntownEmaarDec 202640.2%
Address The BayEmaarDec 202639.3%
BiancaDubai PropertiesDec 202630.2%

Also due in this window: more than a dozen Azizi Riviera buildings in Meydan (registered for March to May 2027, between roughly 30% and 85% built), several Imtiaz and Nakheel projects on Dubai Islands, and early-stage phases at DAMAC Hills. Search for any of them in our projects directory.

What this means if you own a unit

  • Nearly finished (60%+): handover could be months away. Arrange the final payment or completion mortgage now, book a snagging inspection, and decide whether to sell, lease or move in.
  • Big gap between date and progress: plan for a later completion than the registered date, and check your contract for what it says about delays.
  • Everyone: many units in the same building complete at once, so pricing and timing matter. Read our off-plan handover guide.

Umar’s take

The registered date is a starting point, not a promise. The construction percentage tells you far more about when you’ll actually get your keys. If you own in any of these projects and you’re thinking about selling or leasing around handover, plan three to six months ahead: buyers and tenants are comparing your unit with everyone else’s in the same building. Get a free valuation of your unit, and I’ll tell you honestly whether to sell now, at handover, or hold.

Source: Dubai Land Department open data, Real Estate Projects register, snapshot dated 15 June 2026. Construction figures are as recorded on that date; registered completion dates can change. This is general information, not advice on any specific unit.

Free · Weekly

Get Dubai This Week on WhatsApp

My weekly read on the Dubai market, new launches worth a look, and the occasional "don't buy this". Straight to your phone, no spam, leave any time.

Mohammed Umar Zakaria

Mohammed Umar Zakaria, Umar The Realtor

RERA-licensed Dubai real estate advisor (BRN 77022) with Driven | Forbes Global Properties. About Umar

Start a conversation

Tell Umar what you're looking for.

Or WhatsApp

Prefer to talk? Call +971 58 675 5986 or email umar@umartherealtor.com.