The short answer: 48 registered Dubai projects have completion dates between September 2026 and July 2027 in the Dubai Land Department’s latest open data. Some are nearly finished; others are far behind their registered date, which usually means the date will move. If you own a unit in one of them, now is the time to plan your final payment, snagging, and whether to sell, lease or move in.
How to read this
Figures come from the DLD’s Real Estate Projects register (snapshot dated 15 June 2026): each project’s registered completion date and the construction percentage recorded at that time. Construction has continued since then, and registered dates can be revised, so treat this as an early warning, not a final schedule. Tap any project to see its page and follow it: you’ll get an email when the DLD data changes.
Close to completion (60% or more built)
| Project | Developer | Registered completion | Built (June 2026) |
|---|---|---|---|
| The Valley – Elora | Emaar | Sep 2026 | 89% |
| Azizi Riviera 55 | Azizi | Mar 2027 | 85.6% |
| Arabian Ranches III – Anya 2 | Emaar | Dec 2026 | 76.8% |
| Golf Heights | Emaar | Dec 2026 | 70.2% |
| Arabian Ranches III – Anya | Emaar | Oct 2026 | 68.4% |
| Azizi Riviera 56 | Azizi | Mar 2027 | 67.7% |
| The Valley – Rivana | Emaar | Mar 2027 | 64.2% |
| Palm Beach Towers 2 | Nakheel | Dec 2026 | 64.1% |
| Palm Beach Towers 1 | Nakheel | Dec 2026 | 63.6% |
| City Center Residences | Emaar | Sep 2026 | 63.6% |
Watch list: big gap between date and progress
These projects had registered completion dates in 2026 but were less than 30% built in June. A gap this size usually means the completion date will be revised, so check the latest schedule with the developer before you plan around it.
| Project | Developer | Registered completion | Built (June 2026) |
|---|---|---|---|
| Binghatti Aquarise | Binghatti | Oct 2026 | Not started |
| Central Park Plaza, City Walk | Meraas | Oct 2026 | 10.7% |
| Bay Residences, Dubai Islands | Nakheel | Oct 2026 | 19.1% |
| Lanai Island, Tilal Al Ghaf | Majid Al Futtaim | Sep 2026 | 19.4% |
| Mercedes-Benz Places | Binghatti | Dec 2026 | 26.1% |
In progress (30–60% built)
| Project | Developer | Registered completion | Built (June 2026) |
|---|---|---|---|
| Palm Beach Towers 3 | Nakheel | Dec 2026 | 56.9% |
| Marina Shores | Emaar | Dec 2026 | 54.2% |
| Oasis Residences 02, Expo City | Expo City Dubai | Jun 2027 | 48.2% |
| Oasis Residences 01, Expo City | Expo City Dubai | Jun 2027 | 46.7% |
| Sobha Hartland Waves Opulence | Sobha | Sep 2026 | 46.6% |
| Fairway Villas 2, Emaar South | Emaar | Dec 2026 | 45.8% |
| Mudon Al Ranim 7 | Dubai Properties | Sep 2026 | 43.8% |
| Mudon Al Ranim 8 | Dubai Properties | Sep 2026 | 43.2% |
| Beach Gate by Address | Emaar | Dec 2026 | 42.9% |
| The St. Regis Residences, Downtown | Emaar | Dec 2026 | 40.2% |
| Address The Bay | Emaar | Dec 2026 | 39.3% |
| Bianca | Dubai Properties | Dec 2026 | 30.2% |
Also due in this window: more than a dozen Azizi Riviera buildings in Meydan (registered for March to May 2027, between roughly 30% and 85% built), several Imtiaz and Nakheel projects on Dubai Islands, and early-stage phases at DAMAC Hills. Search for any of them in our projects directory.
What this means if you own a unit
- Nearly finished (60%+): handover could be months away. Arrange the final payment or completion mortgage now, book a snagging inspection, and decide whether to sell, lease or move in.
- Big gap between date and progress: plan for a later completion than the registered date, and check your contract for what it says about delays.
- Everyone: many units in the same building complete at once, so pricing and timing matter. Read our off-plan handover guide.
Umar’s take
The registered date is a starting point, not a promise. The construction percentage tells you far more about when you’ll actually get your keys. If you own in any of these projects and you’re thinking about selling or leasing around handover, plan three to six months ahead: buyers and tenants are comparing your unit with everyone else’s in the same building. Get a free valuation of your unit, and I’ll tell you honestly whether to sell now, at handover, or hold.
Source: Dubai Land Department open data, Real Estate Projects register, snapshot dated 15 June 2026. Construction figures are as recorded on that date; registered completion dates can change. This is general information, not advice on any specific unit.